The battery is only one part of a BESS project.

Eight interfaces to review before commissioning — from the grid connection to operational handover.

For project owners, developers, investors and EPC teams. Use these questions to structure a technical discussion; final requirements depend on the approved project, manufacturer and grid operator.

01

Connection boundary

Confirm the agreed import and export limits, metering boundary and operator interfaces. A battery rating alone does not establish the permitted power at the connection point.

02

PCS capability

Review active and reactive capability together, including voltage, temperature and auxiliary-load assumptions. Check the capability at the point of connection, not just at the converter terminals.

03

EMS / PPC interfaces

Define which controller owns each setpoint, how limits are coordinated, and the response to unavailable communications or state-of-charge limits.

04

Transformer & cables

Review equipment ratings, thermal assumptions, cable installation conditions, losses and protection interfaces as one electrical system.

05

Protection & interlocks

Coordinate the protection philosophy, approved settings, authority boundaries and test evidence. This checklist is not a switching procedure or permission to energise.

06

SCADA & signal quality

Verify signal names, units, scaling, timestamps, quality flags and command feedback against an agreed signal list. The online Mercury simulator uses demonstration values, not plant telemetry.

07

Safety & auxiliaries

Review cooling, auxiliary supplies, battery monitoring and fire-system interfaces against the project design and manufacturer requirements.

08

Commissioning evidence

Agree the test boundaries, acceptance criteria, responsibilities, document register and outstanding-action process before handover. Confirm what the operator must witness or approve.

Need an independent review of your project?

Send a non-confidential summary. We agree the scope, fee, deliverable and schedule before payment.

Request a technical reviewExplore the free SCADA simulator

General engineering guidance. No real plant is connected to the simulator. A technical response does not replace authorised design, approved procedures or operator acceptance.